complete

2022

Client

Preventive Maintenance Service Contract

complete

2017

Client

Mandalay Electricity Supply Corporation

33/11 KV 5MVA Substation, Control Building, Switch Yard Construction, 11 KV Transmission Line and 33 KV Transmission Line Construction and Commissioning

complete

2016

Client

Mandalay Electricity Supply Corporation

11KV Transmission Line and 33/0.4 Sub Stations Construction and Commissioning

complete

2016

Client

Mandalay Electricity Supply Corporation

33/11 KV 5MVA Substation, Control Building, Switch Yard Construction, 11 KV Transmission Line and 33 KV Transmission Line Construction and Commissioning

complete

2016

Client

Department of Hydropower Implementation, Ministry of Electricity and Energy

Civil Construction Services

complete

2015

Client

MOGE and MOEP

11KV and 400 V Transmission Line and Sub Station Construction and Commissioning